  1. Remove the upper front panel by using the key that is found on the side of the Datron. Turn the bolts in the upper left hand corner, and upper right hand corner, and take off the panel
    • Remove the upper front panel by using the key that is found on the side of the Datron. Turn the bolts in the upper left hand corner, and upper right hand corner, and take off the panel

  2. remove the vacuum by just loosing the bolt with an allen key as shown in the picture and the tube should slide out.
    • remove the vacuum by just loosing the bolt with an allen key as shown in the picture and the tube should slide out.

  3. Take out the greaser from the husky drawer that is labeled as greaser. push the greaser into the holes shown and squeeze the handle. Take out the greaser from the husky drawer that is labeled as greaser. push the greaser into the holes shown and squeeze the handle.
    • Take out the greaser from the husky drawer that is labeled as greaser. push the greaser into the holes shown and squeeze the handle.

    • After greasing all the holes then put the vacuum and front panel back.

  4. To grease the Y axis, remove the the table as shown in the picture by removing all the bolts.
    • To grease the Y axis, remove the the table as shown in the picture by removing all the bolts.

  5. Remove the caps as shown  in the picture and grease the holes, then replace the caps and the vacuum table.
    • Remove the caps as shown in the picture and grease the holes, then replace the caps and the vacuum table.